- Steam boiler system 5,300kg/h
- Business-optimised design according to the precise determination of needs
- Exhaust gas heat exchanger for heating the feed water
- Flash heat exchanger for heating additional water with the flash steam
- Designed for low-salt operation to reduce blowdown losses
- Water treatment plant, consisting of a softener and a downstream osmosis plant
- Modern gas burner
- Insulation of piping
Result of the new steam boiler system
- Improvement in boiler effectiveness
- Reduction in exhaust gas temperature at full load to 122°C
- High concentration through water treatment
- Reduction in radiation losses
- Increased operational reliability
- Reduction in noise emissions
Services
- General contracting
- Submission of documents to the authorities
- Engineering
- Delivery
- Mechanical and electrical installation
- Measurement and control technology
- Training the operation staff
- Commissioning
The energy efficiency measures were awarded the klimaaktiv Prize on 5 December 2016. The proven saving amounts to 1,185,700 kWh per year.