Relocating the CIP system and container sterilisation system
- Providing advice while the production hall was being rebuilt according to the system requirements
- Systematic shut-down of the old plant
- Disassembly and preparation of transportation including conservation of system components for storage prior to new installation, building handed over in a completely clean state
- Transportation
- Detailed planning of the new system that was to be built and adapted to the new conditions, including integration of new components
- Electrical and mechanical assembly
- Commissioning, training of operating staff, documentation